A Closed Item Still Had an Open Question
How a resolved structural checklist item in Procore masked an unaddressed engineering query, leading to three weeks of field delays.

The Handoff Failure
During the final phases of a commercial laboratory project, the electrical and mechanical systems were nearing completion. A critical RFI regarding the vibration isolation coordinates for the rooftop air handling units (AHUs) was officially marked as "Closed" in the project management software. Because the status indicator showed green, the construction management team assumed all outstanding engineering questions were fully resolved.
However, the closing response from the structural engineer actually contained a conditional request: "Approved, provided that the concrete pad thickness is verified to be nine inches minimum and reinforcement is adjusted accordingly." This note was buried deep in the attachment comments. The checklist item was closed by an administrator who only saw the system status. The field crew proceeded to install the AHUs on the standard six-inch pads that had already been poured, completely unaware of the engineer's conditional requirement.
Tired of Losing Context Between Project Phases?
Join our workshops to audit your current handover protocols and implement a framework that preserves intent and prevents rework.
No automated emails. We respond with a personalized project assessment path.