Case Analysis•Subcontractor Transition

Subcontractor Transition Left Critical Gaps

A case study on how a mid-project trade transition led to missing MEP slab penetrations and how to implement robust coordination handoffs.

June 5, 2026
By Jessica Miller
Subcontractor Transition Left Critical Gaps

The Handoff Failure

During the structural phase of a mixed-use commercial development, the primary concrete subcontractor faced financial distress. This situation forced the general contractor to terminate their contract and rapidly onboard a replacement trade to keep the project on track.

Although the transition occurred over a two-week period, the incoming crew received only the latest IFC (Issued for Construction) drawing set. Critical information was missing from this handover: informal field notes, RFI responses, and coordination emails detailing custom mechanical sleeve locations remained with the outgoing subcontractor.

When the new subcontractor poured the level three slab, they omitted twelve critical MEP penetrations. This oversight resulted in a solid concrete block blocking the scheduled riser pipes, which went unnoticed until the mechanical trade arrived on site to install the vertical risers.

Align Your Next Handoff

Tired of Losing Context Between Project Phases?

Join our workshops to audit your current handover protocols and implement a framework that preserves intent and prevents rework.

No automated emails. We respond with a personalized project assessment path.

Trust copy

ProjectHandoff Casebook is an independent construction publication about project communication and decision context. It does not provide project-management software, host project documents, automate workflows, or connect to Procore. Procore is a trademark of its respective owners. ProjectHandoff Casebook is not affiliated with or endorsed by Procore.